|
3 August 2010
Hindalco announces Q1 FY2010-11 results
Click
here to view the results
|
|
Vs.
Q1 FY10 |
| Revenues |
Rs.5,178 crore
|
33%
|
| PBITDA |
Rs.901 crore
|
8%
|
| PAT |
Rs.534 crore
|
11%
|
Strong Q1 with sharp increase in sales, PBIDTA
and net income
Financial highlights
(In
Rs. crore)
|
Quarter
ended 30 June 2010 |
Quarter
ended 30 June 2009 |
| Net
sales and operating revenues |
5,178
|
3,897
|
| Other
income |
69
|
75
|
| Profit
before depreciation, interest and tax |
901
|
833
|
| Depreciation
|
169
|
165
|
| Interest
and finance charges |
59
|
68
|
| Profit
before tax |
673
|
600
|
| Provision
for taxes |
139
|
119
|
| Net
profit |
534
|
481
|
| Basic
EPS* |
2.79
|
2.83
|
| *EPS
is lower on account of higher equity capital
at Rs.191.37 crore post QIP vs. Rs.170.05
crore in Q1 FY09. |
Hindalco Industries Ltd, an Aditya Birla Group
company, today announced its unaudited financial
results for the quarter ended June 30, 2010.
Its performance in the quarter has been significantly
better than the comparable quarter in the previous
year.
Net sales at Rs.5,178 crore in Q1 FY11 were
up 33% over Q1 FY10, driven by higher volumes,
better product/geographic mix and improved realisation.
Additionally its low cost advantage, arising
from integration and captive coal for own power
generation for the Hirakud smelter, cushioned
the adverse impact of spiralling cost escalations
of crude and crude derivatives as well as purchased
coal for Renukoot and plummeting copper TcRc
The company also benefitted from higher aluminium
LME and better by-product realisation in its
copper business. Other income and interest/
financing charges were constrained by lower
returns on investment and lower average interest
rate respectively.
Profit before tax is higher by 12% at Rs.673
crore vis-à-vis Rs.600 crore in Q1 FY10.
Net profit is at Rs.534 crore as against Rs.481
crore in Q1 FY10.
.Business segment results
Of the total revenues of Rs.5,178 crore, aluminium
business contributed Rs.1,867 crore with an
EBIT of Rs.552 crore. Aluminium sales were higher
on the back of higher volume, better mix, along
with better LME compared to Q1 FY10. These benefits
were eroded partly by the appreciating Rupee
and higher energy cost. The increase of 32%
in revenue translated into an EBIT gain of 21%
at Rs.552 crore in Q1 FY11 from Rs.455 crore
in Q1 FY10.
In the copper business, revenues were higher
at Rs.3,314 crore up by 34% from Rs.2,479 crore
in Q1 FY10, mainly on account of higher copper
LME. However, the copper business being a custom
smelting operation, with offset hedging program,
was not significantly impacted by the gain or
loss on changes in LME. Lower TcRc, higher energy
cost and appreciating Rupee dented the margins,
despite better efficiencies and improved mix.
The copper business performance is to be seen
in the light of planned shutdown of a smelter
for 24 days in April 2010. The results of copper
business, adjusted for this shutdown, are superior
compared to Q1 FY10.
Hirakud outage: Operations of the aluminium
smelter at Hirakud have been affected in July
2010 due to continuous bad weather with heavy
rains and lightning. A team of experts have
now completed the assessment of the situation
and have formulated an action plan for quick
revival of operations as well as certain remedial
actions for the future. In line with the action
plan currently under implementation, electrolytic
cells taken out of circuit will be restarted
in a phased manner. This exercise is expected
to be completed by end-August 2010. As a consequence
of this unforeseen outage, the Hirakud aluminium
production is expected to be lower by around
20,000MT for the current fiscal. Efforts are
being made to contain the impact of the loss
by appropriate management action to optimise
profitability across all other business segments
of the company. The company has a comprehensive
mega insurance policy which covers property
damage and business interruptions.
Strategic initiatives
Utkal Alumina International Limited [UAIL]:
UAIL, which is a 100% subsidiary of Hindalco,
is setting up a 1.5mtpa alumina refinery in
Rayagada district of Orissa. The project will
feed the alumina requirements of the Mahan and
the Aditya smelters presently under construction.
Hindalco has successfully achieved the financial
closure of UAIL with the signing of a common
loan agreement of Rs.4,906 crore on July 28,
2010. This constitutes the entire debt requirement
of the project. The loan documents were signed
in Bhubaneswar by a group of 28 banks. The syndication
is led by IDBI Bank with SBI Caps and The Royal
Bank of Scotland NV as joint arrangers and book
runners.
The equity requirement for this project has
already been tied up. This project is expandable
to 3mtpa at relatively lower incremental capital
cost. This is a significant milestone in Hindalco's
strategy to grow its alumina capacity and play
the entire value chain in aluminium.
Operational review
Aluminium
Total alumina and metal production is up by 9%
and 3% respectively. Wire rod production also
rose up by 6% in Q1FY11. Downstream production
grew by 4% and 9% each in the case of flat rolled
products and extrusions respectively, compared
to Q1 FY10.
| Production
(MT) |
Q1
FY11
|
Q1
FY10
|
| Alumina |
341,419
|
311,917
|
| Metal |
140,061
|
135,439
|
| Wire rod |
23,326
|
22,104
|
| Flat
rolled products |
51,373
|
49,304
|
| Extrusions |
9,617
|
8,812
|
Copper
Quarterly cathode production has been lower due
to the planned smelter shutdown. The value added
CCR production is up 38% on the back of increased
capacity.
| Production
(MT) |
Q1
FY11
|
Q1
FY10
|
| Copper
cathodes |
76,309
|
79,782
|
| CC
rods (own production) |
40,708
|
29,461
|
Brownfield expansion projects
Hirakud smelter expansion: The smelter
expansion from 155KTPA to 161KTPA is scheduled
for completion by Q2 FY11. Smelter expansion
from 161 to 213KTPA along with 100MW power plant
expansions will be completed in Q4 FY12. Site
activities like boundary wall and area grading
are progressing well. BTG order has been placed
and other major orders are to be finalised in
the next quarter.
Further to the above, the smelting capacity
at Hirakud is intended to be expanded from the
proposed 213KTPA to 360KTPA with a corresponding
increase in back-up captive power from the proposed
467.5MW to 967.5MW.
Hirakud flat rolled products project:
This project is underway for the transfer of
all key equipment from the Novelis Plant at
Rogerstone, UK to Hirakud. This will enable
us to produce can-body stock for local and export
markets. The project is slated for completion
in Q2 FY12. Dismantling activities are progressing
well and are around 98% complete. Most of the
major orders for refurbishment of existing equipment
and procurement of new equipment have been placed.
A strong project team is in place.
Belgaum special alumina project: The
special alumina production from Belgaum is proposed
to be ramped up to 316KTPA from 138KTPA. To
reduce the cost of production substantially,
a proposal for an 18MW co-gen power plant and
a railway siding facility are also being evaluated.
Greenfield projects
Utkal Alumina Project (UAIL): The construction
of 1.5 Mio tpa alumina refinery along with a
90MW captive co-gen plant is in full swing.
The output from UAIL would be sufficient to
feed alumina to the Mahan and the Aditya smelters.
Engineering for refinery and captive co-gen
plant is nearing completion. Contractors are
working at the site for civil and structural
work and have mobilised more than 5,000 people.
Piling, fabrication, concreting and tank erection
are all well underway. Major equipment like
boilers, evaporators and turbines have started
arriving at the site and erection and structural
work for the various equipment is in progress.
Orders for all the long delivery equipment have
been placed. Around 82% of the project cost
has already been committed. The production of
alumina is expected to start around Q2 FY12.
Mahan aluminium project: A 359KTPA aluminium
smelter capacity along with a 900MW captive
power plant is coming up in Bargwan, Madhya
Pradesh.
Major approvals are in place and site activities
are on schedule. Around 10,000 people are working
at the site. Site grading work, boundary wall
and piling are nearing completion. Concreting
and structural work is progressing in line with
the first pot start up schedule. Work on boiler
foundation, ESP, powerhouse units and chimney
rafts is progressing in full swing. Erection
of engineering structure for boilers is in progress.
Major equipment has started arriving at the
site. Around 82% of the total project cost has
been committed. The first metal from the smelter
is expected by Q2 FY12.
Aditya aluminium project: A 359KTPA aluminium
smelter along with a 900MW captive power plant
is coming up in Orissa.
Major approvals are in place. Major orders have
been placed for both the smelter and the power
plant. Around 59% of the total project cost
for the smelter and power plant has been committed.
Site activities like area grading, boundary
wall are in progress. The first metal from the
smelter is expected by Q3 FY12
Aditya refinery project: A 1.5 Mio TPA
alumina refinery along with a 90MW co-gen plant
is coming up in Orissa. This is a replica of
the Utkal alumina refinery. The refinery would
be mechanically complete by Q1 FY14.
Jharkhand aluminium project: A 359KTPA
aluminium smelter along with a 900MW captive
power plant is coming up in Sonahatu, Jharkhand.
This is a replica of the Aditya / Mahan smelter.
The land acquisition process has already started.
Activities for getting environmental clearance
have started and a presentation has been made
to the MOEF expert committee. The Tubed coal
mine has been allotted jointly with Tata Power.
The first metal from the smelter is expected
by
Q1 FY14.
Industry outlook
Aluminium
Global aluminium demand in Q1 FY11 reflected
good growth of 24% over Q1 FY10. A strong growth
in Asia has been propelled by Chinese growth,
and was partly supported by a "low-base"
effect. The key drivers of growth in North America
and Europe were the auto and building sectors.
Japan, too, had good growth in flat rolled products,
extrusions and castings. Pick-up in consumption
led to a slight drop of 0.17mt in LME stocks
reaching 4.42mt at the end of June.
A strong demand enabled LME to reach USD2,400/t
levels in April but due to European fears, the
quarter ended at USD1,900 levels. Going forward,
LME is likely to be supported by the cost pressures,
especially in China, although further gains
would be contingent upon improvement in risk
appetite in financial markets.
Indian industry had a nominal growth of 8%
on Y-o-Y basis. Major growth areas were the
electrical sector and castings for the auto
Industry. The global demand is expected to continue
to be good in Q2, though the base-effect will
start to get diluted.
Copper
Global copper consumption continued to improve
in the last quarter. The world refined copper
market balance was in a small deficit in the
first four months of 2010 after recording large
surpluses in the previous two years. Exchange
stocks at end-June 2010 were at 646,000tonne
recording a drop of 107,000tonne over the quarter.
Despite this, copper prices at the LME exhibited
weakness on account of increased risk aversion.
World copper consumption is likely to continue
to grow in the coming quarters on improving
demand from emerging countries. The outlook
for refined copper consumption in India remains
robust, given the continued growth momentum
in the economy.
Strong concentrates demand from China and stagnant
world mine production continued to keep the
concentrates market in deficit which led to
spot TcRcs (Treatment and Refining Charges)
decline to low single-digit during the current
quarter. TcRcs under mid-year negotiations for
current year dropped by about 20% over the previous
year. There are no signs of any significant
improvement in the concentrates market scenario
in immediate future.
Company outlook
Aggressive and innovative approaches for low
cost brownfield expansions, sweating of existing
assets, continuous cost reduction and optimising
working capital continue to yield results despite
inflationary conditions. The outlook for the
coming quarters will be impacted by a subdued
financial market sentiment, uncertain commodity
and financial markets and lower production at
Hirakud. The company is determined to tide over
these negatives because of its strong fundamentals
and committed resources.
The progress in the greenfield projects and
their activity levels are expected to further
accelerate during the year.
Statements in this "Press Release"
describing the company's objectives, projections,
estimates, expectations or predictions may be
"forward looking statements" within
the meaning of applicable securities laws and
regulations. Actual results could differ materially
from those expressed or implied. Important factors
that could make a difference to the company's
operations include global and Indian demand
supply conditions, finished goods prices, feed
stock availability and prices, cyclical demand
and pricing in the company's principal markets,
changes in Government regulations, tax regimes,
economic developments within India and the countries
within which the company conducts business and
other factors such as litigation and labour
negotiations. The company assume no responsibility
to publicly amend, modify or revise any forward
looking statement, on the basis of any subsequent
development, information or events, or otherwise.
For more information, contact:
Dr. Pragnya Ram,
Group Executive President,
Corporate Communications,
Aditya Birla Management Corporation Private Limited
Tel: 91-22-6652 5000 / 2499 5000
Fax: 91-22-6652 5741/ 42
Email: pragnya.ram@adityabirla.com
|